2019 Red Hill Median Improvement Project
The Town has begun construction of the Red Hill Median Improvements Project. The project consists of removing the existing diseased elm trees and installing bioretention, irrigation, drainage improvements, curbing, landscaping and trees. This project was made possible by a generous private donation. Plans can be found here:
https://www.townofsananselmo.org/DocumentCenter/View/24962/Red-Hill-Median-Improvements-Plans-PDF
Tentative schedule as follows:
Phase 1 – Retaining Wall (Van Midde & Sons)
Monday 8/26: 9:30 am - 4 pm, 7 pm - 11 pm
Tuesday 8/27: 10 am - 2 pm, 7 pm - 11 pm
Wednesday 8/28: 10 am - 2 pm, 7 pm - 11 pm (no lane closures EB SFD to Red Hill)
Thursday 8/29: 10 am - 2 pm, 7 pm - 11 pm (no lane closures EB SFD to Red Hill)
Phase 2 – Median Improvements (Ghilotti Const. Co. – GCC)
Starts Wednesday August 28, continues thru mid-January. The majority of work to be completed by the end of December, with punch list items continuing into January.
Work hours 8 am to 5 pm, with any lane closures limited to 9 am to 3 pm.
Some elements of the work will require lane closures on SFD and Center, however, most lane closures will be on Red Hill.
This information will be updated as frequently as possible. Please plan your commute with this project in mind. The Town appreciates your patience during this project to help beautify the Town.
Updates will be available on the project page at https://www.townofsananselmo.org/1328/15584/Red-Hill-Median.