[ARCHIVED] 2019 Red Hill Median Improvement Project

180323 Median Sketch

The Town has begun construction of the Red Hill Median Improvements Project. The project consists of removing the existing diseased elm trees and installing bioretention, irrigation, drainage improvements, curbing, landscaping and trees. This project was made possible by a generous private donation. Plans can be found here:

https://www.townofsananselmo.org/DocumentCenter/View/24962/Red-Hill-Median-Improvements-Plans-PDF

Tentative schedule as follows:

Work for the week of September 16-20 includes:

  • Remove guardrail
  • Grind stumps and remove roots
  • Clear and grub median
  • Rough grade swales
  • Begin stormdrain modification

The work started Wednesday August 28, continues thru mid-January. The majority of work to be completed by the end of December, with punch list items continuing into January.

Work hours 8 am to 5 pm, with any lane closures limited to 9 am to 3 pm.

Some elements of the work may require lane closures on SFD and Center, however, most lane closures will be on Red Hill.

This information will be updated as frequently as possible. Please plan your commute with this project in mind. The Town appreciates your patience during this project to help beautify the Town.

Updates will be available on the project page at https://www.townofsananselmo.org/1328/15584/Red-Hill-Median.

Facebook Twitter Email

Other News in Town Spotlight

LOTA2023nlogo

Live on the Avenue 2023!

Posted on: May 23, 2023
Blasden 60 percent rendition

Reimagine Creek Park 60% Design Review

Posted on: September 11, 2023
Rental Policies Instagram image

San Anselmo Residential Rental Policies

Posted on: August 23, 2023